Reinforced Concrete Pool Demolition in Thornhill
DRM Cutting removed a reinforced concrete pool shell during the renovation of a basement spa at a community centre at 770 Chabad Gate in Thornhill. The demolition scope took approximately one month and included cutting and hauling out the concrete, excavating soil and removing the old partitions.

Hydraulic concrete cutting inside the basement
The pool shell was reinforced, so the crew used a hydraulic saw to divide the concrete into sections. Demolition breakers broke down the remaining concrete for removal. The cut lines and sections are visible in the photos from the first documented stage.

Concrete haul-out and excavation
The crew removed and hauled away the broken concrete, then excavated soil from the work area. The later photos show where concrete had been removed and the reinforcement and surrounding fill had become visible.

Removing the old spa partitions
DRM also removed the interior partitions from the former spa layout. The approximately one-month duration covers the entire demolition and excavation scope, including the partitions and haul-out.